Connect with us

Hi, what are you looking for?

Investing

Pilot Plant Commences First Phase of Operations

Pursuit Minerals Ltd (ASX: PUR) (“PUR”, “Pursuit” or the “Company”) is pleased to provide the following update on key developments for its Lithium Carbonate Pilot Plant which has commenced the first phase of operations to produce Lithium Carbonate.

HIGHLIGHTS

Pilot Plant commissioning complete with first phase of operations for the production of Lithium Carbonate underway.Completion of dynamic simulation, mass balances and plant layout design conceptually producing 250 tonnes per annum of 99.95% battery grade Lithium Carbonate via conventional evaporation process method.Engagement of Ausenco to complete independent peer review study of the 250 tonne per annum plant design, block flow process, and evaporation pond design.Engagement of highly experienced engineering team to oversee and manage plant operations and first production of Lithium Carbonate.

The Company has completed the commissioning works of the Lithium Carbonate Pilot Plant and will now begin operations with the overall goal of producing battery grade Lithium Carbonate. The Pilot Plant will look to produce an initial sample batch using synthetic brine of approximately 50-100kg of product.

Following completion of this milestone, evaporated brine, currently being sourced from the Stage 1 Drilling Program, will be utilised to produce approximately 2 to 10 tonnes of Lithium Carbonate products anticipated to be battery grade product. After this, the Company will consider relocation of the Pilot Plant to site following the completion of construction and filling of evaporation ponds to provide feed for the plant.

In relation to the commencement of operations at the plant, Pursuit Managing Director & CEO, Aaron Revelle, said:

“The Rio Grande Sur Project continues to advance toward first production at a significant pace. With plant operations now underway, we look forward to the production of the first Lithium Carbonate products demonstrating the enormous potential of the Rio Grande Sur Lithium Project.”

In conjunction with our Stage 1 drilling program which is currently underway and the potential upgrade to our existing JORC resource, we continue to make significant progress on multiple fronts as we move toward becoming a Lithium producer. To this end, we continue to progress the environmental permitting applications to commence construction of the evaporation ponds which is currently being targeted for this year. The entire team is very excited about the production process, and we look forward to reporting on the results over the coming months.”

Click here for the full ASX Release

This post appeared first on investingnews.com

Enter Your Information Below To Receive Free Trading Ideas, Latest News And Articles.






    Your information is secure and your privacy is protected. By opting in you agree to receive emails from us. Remember that you can opt-out any time, we hate spam too!

    You May Also Like

    Editor's Pick

    LIVE OAK, Fla. — President Biden traveled to Florida on Saturday to survey the damage caused by Hurricane Idalia, part of a storm response...

    Stock

    President Biden is asking his Cabinet to ‘aggressively execute’ plans for federal employees to return to their offices for work this fall after years...

    Stock

    A group of House Democrats penned a letter Thursday to several top Biden administration and White House officials, demanding the immediate continuance of uninterrupted...

    Stock

    Special Counsel Jack Smith proposed to begin former President Donald Trump’s trial in January 2024 for the charges he’s facing in relation to the...

    Disclaimer: beneficialinvestmentnow.com, its managers, its employees, and assigns (collectively “The Company”) do not make any guarantee or warranty about what is advertised above. Information provided by this website is for research purposes only and should not be considered as personalized financial advice. The Company is not affiliated with, nor does it receive compensation from, any specific security. The Company is not registered or licensed by any governing body in any jurisdiction to give investing advice or provide investment recommendation. Any investments recommended here should be taken into consideration only after consulting with your investment advisor and after reviewing the prospectus or financial statements of the company.


    Copyright © 2023 beneficialinvestmentnow.com